Temporary Traffic Regulation Order – S14 Road Traffic Regulation Act 1984
Temporary Road Closure at – Hethe, Hardwick Road
A request has been received from SSE for a temporary road closure to apply to a section of Hardwick Road, whilst essential electrical works (replacement of vulnerable overhead and new underground 11kv electric cable) are carried out.
A Temporary Traffic Regulation Order (TTRO) is being made to implement the temporary closure and will operate from 11/05/2020 at (00:00hrs).
The anticipated duration of the work to complete is 5 weeks (full closure 24hrs each day).
(The maximum duration of a TTRO on a road is 18 months and on a footpath is 6 months, or until completion of the works, whichever is the earlier.)
Notice of intention to make the Order will be published in the local press.
A copy of the drawing showing the extent of the closure and also the alternative route for traffic is attached.
S-14(1) Notice of Order (for distribution) – T7518 – Hethe Hardwick Road
TM Plan – SSE-HARDWICH ROAD-BICESTER-OX278HA-ROAD CLOSURE
Further information regarding the works may be obtained by contacting ‘Jamie Dougall’ of ‘SSE’ on 07515372114.
T7518/MR