As you may be aware, we‘re carrying out essential works on the M40 at junction 10 to widen the southbound exit slip road into three lanes as it approaches the A43 Padbury roundabout.
During the last phases of the scheme we’ll require weekend closures. These are currently programmed for:
- Friday 9 May, 9.30pm until 6am – A43 closed between Baynard green & Cherwell Southbound.
- Saturday 10 May, 9.30pm until 6am – A43 closed Cherwell to Baynards Green North bound.
- Sunday 11 May, 9.30pm until 6am – A43 closed between Baynards Green & Cherwell Southbound.
Our ref: 604237
- Monday 12 to Friday 16 May, 09.30pm until 6am – M40 J10 SB exit slip closed
- Saturday 17 & Sunday 18 May, 09.30pm until 6am – A43 closed Cherwell to Baynards Green North bound including M40 J10 SB exit slip closed.
Please accept our apologies for any disruption these works may cause. We always aim to work to the programme, however unforeseen circumstances or adverse weather conditions may mean changes.
To keep updated with this work please visit: https://nationalhighways.co.uk/our-roads/east-midlands/east-midlands-maintenance-schemes/
If you have any questions about this work, please contact National Highways Customer Contact Centre on 0300 123 5000 open 24/7, who will direct your enquiry to the most appropriate person, or email: info@nationalhighways.co.uk
Further details can be found at: www.oxfordshire.gov.uk/m40-junction10
Earlier news……………
M40 J10 Padbury Update Notification Letter – the latest news 28 February 2025
Notice from National Highways:
I am emailing to let you know about some upcoming road works planned on the M40.
June 2024 until Summer 2025, we will be carrying out essential improvement works on the southbound section of the M40 at Junction 10 Padbury where it meets the A43. This is a busy junction and this much needed work will increase capacity and extend the life of the road.
During our scheme of work, we will:
- Widen the southbound slip road to three lanes as it enters the roundabout
- Provide smart signals at all the junctions
- Protect the local environment and clearing overgrown vegetation
We need to have traffic management in place to safely complete the works. It will be as follows:
• Weekday daytime (6am to 9:30pm) – temporary 50mph speed limit with southbound slip road remaining open,
• Weekday night time (9:30pm to 6.00am) – closure of the M40 southbound exit slip with the diversion to Junction 9 and back
• 24 hour lane closures of the M40 southbound approach nearside lane
• 24 hour lane closures of A43 north and southbound with temporary 50mph speed limit
• Occasional weekday night time (9:30pm to 6.00am) closures of the sections of the A43 northbound or southbound
Once completed, all road users will benefit from improved road safety and lower journey times through the junction.
For more you can contact our Highways England Customer Contact Centre as follows:
Website: Road closure report – National Highways
Email: info@nationalhighways.co.uk
Telephone: 0300 123 5000
If you have any questions or queries please do come back to me.
Yours,
Mark Fox.
Communications Manager| AmeyConsulting
M: 07714146600
Please note that all our planned roadworks may be subject to change due to weather